WEEK OF JANUARY 13, 2020:
Monday: Line Crew – Hospital Force Main Repair
Camera Crew- Paving List
Pump Crew – Cross Creek Pump Replacement/ work list generated by weekend Lift station run
Tuesday: Line Crew – 1223 Noel Ave Tap
Camera Crew – Paving List
Pump Crew – Replace Defective Pump @ Harley Lane and finished work list from weekend
Wednesday: Line Crew – Assisted Pump Crew to prepare for potential weather event
Camera Crew – Paving List and Camera Work At WWTP
Pump Crew – Martin Mall Pipe evaluation, Lakeshore 1 Starter Replacement
Thursday: Line Crew – Assist Camera Crew with Traffic Control on Chickasaw Drive, Finish Prep for Potential Weather Event.
Camera Crew – Chickasaw Drive Camera Work
Pump Crew – Fueling Stationary Generators/ Building Maintenance at Lift Stations
Friday: Line Crew – Shop and Equipment Maintenance/ Manhole Evaluations (if weather allows)
Camera Crew – Paving List (if weather allows)
Pump Crew – Building Maintenance at Lift Stations
WEEK OF DECEMBER 23, 2019:
Monday: Line Crew- Job Prep for Noel Ave Tap/ Assist Vactor with Traffic Control on Chickasaw Drive
Camera Crew- Paving List
Pump Crew – Install Repaired Pump at Hospital Lift Station.
Tuesday: Holiday
Wednesday: Holiday
Thursday: Line Crew- Assist Camera Crew with Traffic Control
Camera Crew- Paving List
Pump Crew- Lift Station run
Friday: Line Crew- Assist Camera Crew with Traffic Control
Camera Crew- Paving List
Pump Crew- Lift Station run
WEEK OF DECEMBER 16, 2019:
Monday: Line Crew- CDF 908 Pride Ave/ Reed Ave Manhole Repair/ Manhole List and Manhole Evaluations
Camera Crew- Paving List
Pump Crew – Maintenance @ Old WWTP/ Dismantle and evaluate Hospital Pump
Tuesday: Line Crew- Cold Mix 908 Pride Ave/ Manhole List and Manhole Evaluations
Camera Crew- Paving List
Pump Crew – Draw Down Test List
Wednesday: Line Crew- 503 Alan Drive Main Repair
Camera Crew- Paving List
Pump Crew- Maintenance @ Old WWTP
Thursday: Line Crew- Manhole List and Manhole Evaluations
Camera Crew- Paving List
Pump Crew- Generator Maintenance
Friday: Line Crew- Manhole List and Manhole Evaluations
Camera Crew- Paving List
Pump Crew- Generator Maintenance
WEEK OF NOVEMBER 25, 2019:
11/25/19 Line Crew 2804 Country Club Lane (Main Repair)
Pump Crew Generator Inspections
Camera Crew Paving List
11/26/19 Line Crew 614 Choctaw Drive Road Repair
Pump Crew Maintenance Pump Station Lighting
Camera Crew Paving List
11/27/19 Line Crew 5092 Rosemont (Retire Service)
Pump Crew Maintenance and Draw Down Testing Hospital LS
Camera Crew Paving List
11/28/19 Holiday
11/29/19 Holiday
WEEK OF NOVEMBER 18, 2019:
11/18/19 Line Crew- 614 Choctaw Main Repair
Pump Crew - Install Float hangars
Camera Crew – Paving List, locate taps
11/19/19: Line Crew - Traffic Control Technician Training
Pump Crew – Traffic Control Technician Training
Camera Crew - Inspection for Engineering Department, Paving List
11/20/19: Line Crew - 1055 Briarwood Manhole Replacement
Pump Crew - Draw down testing
Camera Crew - Paving List
11/21/19: Line Crew - 2804 Country Club Lane Main Repair
Pump Crew - Install Float Hangars
Camera Crew - Paving List
11/22/19: Line Crew - Stormwater Pollution Prevention work at 604 McCoy Ave.
Pump Crew - Training Lift station inspections
Camera Crew - Paving List
WEEK OF NOVEMBER 4, 2019:
11/4/19: Line Crew - Ken Mel Drive Repair/ Raise Bassett Ave Manholes
Pump Crew – Install float hangars
Camera Crew – Paving List
11/5/19: Line Crew - 421 Thompson (Relocate 415 Thompson Ave Tap)
Pump Crew – Rebuild pump
Camera Crew – Paving List
11/6/19: Line Crew - East Broadway Repair
Pump Crew – Install Float Hangars
Camera Crew – Paving list
11/7/19: Line Crew - 762 North Seminary
Pump Crew – Draw Down Testing
Camera Crew – Paving list
11/8/19: Line Crew - Dirt work List (if conditions allow)
Pump Crew – install float hangars
Camera Crew – paving list
Some work rescheduled from last week due to rainfall
-Dirt Work at various address
WEEK OF OCTOBER 28, 2019:
10/28/19 – Line Crew - Raise manholes Bassett Ave, / Groves sewer testing
Pump Crew – Oil change generators
Camera Crew – Paving list (camera down 10/23 & 24)
10/29/19- Line Crew – Raise Manholes Deep Creek / Groves sewer testing
Pump Crew – Replacing float hangars
Camera Crew – paving list
10/30/19- Line Crew – East Broadway Repair
Pump Crew – Replacing Float hangars
Camera Crew- Paving list
10/31/19- Line Crew Asphalt repair Brent Drive & Mooreland Ave.
Pump Crew – Replacing float hangars
Camera Crew – Paving list
11/1/19 Line Crew – Dirt work list
Pump Crew – Draw down Testing
Camera Crew – Paving List
Dirt work List: 920 N. Main
2168 Brent Drive
1890 Wildwood Drive
631 Stone Lane
18 Valley Drive
338 Murray Street
1013 Ballard Lane
1017 Ballard Lane
WEEK OF OCTOBER 14, 2019:
10/14/19
Line Crew – CDF Browning Street & Silkwood sewer repair, Raise manholes on Ayer Drive
Pump Crew – Change oil in Earlington and Mooreland Ave. Generators
Camera Crew – Camera Paving List
10/15/19
Line Crew - Repair Driveway at 609 Park Ave. from previous repair, raise manholes on Deep Creek
Pump Crew – re-work float systems in multiple lift station to reduce future problems.
Camera Crew – Paving List
10/16/19
Line Crew – Replace sewer tap 338 Murray
Pump Crew – Re-work float systems in multiple lift stations to reduce future problems
Camera Crew – paving list
10/17/19
Line Crew – Raise manholes in Yorktown
Pump Crew – Re-work float system in multiple lift stations to reduce future problems
Camera Crew – paving list
10/18/19
Line Crew - 723 Gentry Lane – main repair, repair tap for new Ideal Station.
Pump Crew – Repair lighting in pump stations, clean panels at lift stations.
Camera Crew – paving list



Brown Road Sewer Replacement Project October 2019